- To: gcdev@sseos.lbl.gov, Tom Throwe <throwe@bnl.gov>, James Flanagan <jimfl@bnl.gov>, Dave Morrison <morrison@bnl.gov>, "Bruce G. Gibbard" <gibbard@bnl.gov>, "Razvan N. Popescu" <popescu@bnl.gov>, Alison Tilp <tilp@bnl.gov>, Shigeki Misawa <misawa@bnl.gov>, Mark Baker <mdbaker@bnl.gov>, Yuri Fisyak <fisyak@d01.phy.bnl.gov>, Garcia-Solis Edmundo <garcia@enp.umd.edu>, Flemming Videbaek <videbaek@bnl.gov>, Torre Wenaus <wenaus@bnl.gov>, Yasushi WATANABE <watanabe@bnl.gov>, John Erskine <John.Erskine@mailgw.er.doe.gov>, Don McLeod <mcleod@uic.edu>
- From: Shigeki Misawa <misawa@bnl.gov>
- Date: Tue, 11 Aug 1998 16:01:03 -0400
- Reply-To: misawa@bnl.gov
At the request of various MDC-1 participants, I have drafted a
"suggested" MDC-1 schedule.
Aug 24 - Sept 7 --> Pre-staging of raw data into HPSS (Possibly
staggered).
Sept 8 - Sept 9 --> "Horizontal" raw data sinking test.
Sept 10 - Sept 15 --> Staggered bootstrapping of experiment
reconstruction software.
Sept 16 - Sept 21 --> Horizontal reconstruction test.
Sept 22 - Sept 24 --> Grand Challenge/Other Data Mining Test
Sept 25 - Sept 30 --> Reconstruction revisited.
Sept 30 - Oct 5 --> Grand Challenge revisited.
Oct 6 - Oct 12 --> Configuration testing (1 Vertical, 2 Vertical,
inter-machine, intra-machine) Experiment
participation is expected, but not necessarily
all at the same time.
Comments welcome.
Shigeki